The project involves maintenance dredging and furnishing a pile driver crew for repairs to docks and waterfront facilities for the Port of Oakland.
Major Challenges
One of the major challenges is berth dredging at one of the West Coast’s largest container terminal facilities while maintaining operations.
Project Highlights
A key highlight of the project is the flexibility in the schedule to keep the container vessel berths open during the dredging operations.
Project Scope
The project scope is to provide all labor, equipment, materials, and incidentals required to dredge Berths 55, 56, 57, 58, and 59, and dispose of the dredged material at Montezuma in compliance with all applicable regulatory and permitting requirements.